This story has been updated with more information about the Aquatic Center pool closures.
By Bryan Boggiano
City officials gave a tentative timeline of pool closures at the Coral Springs Aquatic Center on Wednesday, stating some pools could be closed for up to six months.
The development came as the city commission approved a $3.1 million contract with Recreational Design and Construction, Inc. to make improvements to the Aquatic Center’s pool deck. Costs include design, construction, and renovation.
In September 2022, a consultant study confirmed the deck was shifting because of leaks in the dive well and water intrusion throughout the deck. The firm recommended mitigating the issue immediately to avoid further damage to the decks or competitive pools.
Parks and Recreation Director Rob Hunter said the tentative closing date for the pool is July 22. Work on the pools will take place daily between 7 a.m. and 9 p.m. The project will continue through roughly Jan. 15, and he said the aim is to have the pools reopen between mid-January and February.
He said that will allow Olympic athletes to use the facility for part of their training.
During the deck’s renovation, the Aquatic Center’s fitness facility will remain open, but it will be closed for one unspecified week to repair a crack contractors found during an inspection.
“It’s a project that needs to be done,” Hunter said.
Throughout the duration of the project, swim lessons and classes will take place at Cypress Pool and Mullins Pool. There will be unspecified changes to the public swim schedules at both pools. The city will accommodate local high school swim teams at Mullins Pool.
Members of contracted swim groups, including synchronized swimming, dive clubs, and the Coral Springs Swim Club are encouraged to contact their group leaders for further instructions.
Hunter also mentioned the city will conduct a public outreach initiative to educate residents and those affected by the closures.
Tentatively, the contractor plans to work from west to east, which could allow the Aquatic Center’s 25-meter pool to remain open for longer. However, Hunter said this all depends on the contractor’s findings and a review of the construction as the project progresses.
Despite the nearly six-month projected closure, Hunter said there is an incentive for contractors to have the project complete by Dec. 15.
Vice Mayor Shawn Cerra moved to approve the contract. Commissioner Joshua Simmons seconded. The city commission approved it unanimously.
“This is a big undertaking, this is a big job,” Hunter said. “It took us a long time to get to this point.”
Send Your News to Coral Springs #1 Award-Winning News Site Here. Don’t miss reading Parkland Talk, Tamarac Talk, Coconut Creek Talk, and Margate Talk.
Author Profile

- Bryan has a degree in journalism from the University of Florida and earned his masters in geosciences from Florida International University, where he focused in atmospheric sciences. His interests include weather, entertainment, and municipal government.
Related
NewsSeptember 19, 2023Coral Springs Tightens Regulations on Sober Homes and Recovery Residences Amid Rising Substance Abuse Concerns
NewsSeptember 19, 2023Residents Rally Against Proposed City Village, Fear Loss of Suburban Charm and Safety Concerns
EventsSeptember 12, 2023Memorial Service and Reception for Tom Powers to be Held Sept 18
NewsSeptember 11, 2023Panthers Warrior Hockey Unites First Responders in Tribute to 9/11 Heroes